Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by ______.

admin2011-01-20  21

问题 Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by ______.

选项 A、executive IT manager
B、project manger
C、change control board
D、project sponsor

答案C

解析 项目变更可以由IT经理(executive IT manager)、项目管理者(project manager)、项目发起人(project sponsor)等任意项目干系人发起,但只能由变更控制委员会(change control board)授权通过,所以选C。