Schedule compression shogens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,

admin2018-10-14  28

问题 Schedule compression shogens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and(    ).

选项 A、fast tracking
B、what—if scenario analysis
C、resource leveling
D、critical chain method

答案A

解析
转载请注明原文地址:https://jikaoti.com/ti/MCm7FFFM
0

相关试题推荐
最新回复(0)