Your project is behind schedule due to conflict between team members.Having resolved the conflict,to get the project back on sch

admin2018-10-14  58

问题 Your project is behind schedule due to conflict between team members.Having resolved the conflict,to get the project back on schedule,you should consider(    ).

选项 A、crashing the schedule
B、performing resource leveling
C、conducting reverse resource allocation scheduling
D、utilizing the critical chain resources

答案A

解析
转载请注明原文地址:https://jikaoti.com/ti/FCm7FFFM
0

相关试题推荐
最新回复(0)