During the project,requirements change for a variety of reasons.As needs change and as work proceeds,additional requirements are

admin2014-11-05  68

问题  During the project,requirements change for a variety of reasons.As needs change and as work proceeds,additional requirements are derived and changes may have to be made to the existmg requirements· It is essential to manage these additions and changes efficientlv and effectively.To effectively analyze the impact of the changes,it is Fiecessarythat the sOurce of each requlrement is known and the rationale for any change is documented.The project manager may,howeVer,want to track appropriate measures of requirements volatility to judge whether neW 0r revised(45) are necessary.

选项 A、proceedings
B、controls
C、forecasting’s
D、prelibations

答案B

解析