(19)is the budgeted amount for the work actually completed on the schedule activity or WBS comPonent during a given time period.

admin2009-09-20  44

问题 (19)is the budgeted amount for the work actually completed on the schedule activity or WBS comPonent during a given time period.

选项 A、Planned value
B、Earned value
C、Actual cost
D、Cost variance

答案B

解析 挣值是在给定时期内按进度活动或WBS部件所实际完成工作的预算值。
转载请注明原文地址:https://jikaoti.com/ti/qyy7FFFM
0

相关试题推荐
最新回复(0)