(71) is a method of constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to repres

admin2019-06-06  40

问题 (71) is a method of constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activities and connects them with arrows that show the dependencies. This method includes following types of dependencies or precedence relationships:(72),the initiation of the successor activity,depends upon the completion of the predecessor activity.(73),the initiation of the successor activity,depends upon the initiation of the predecessor activity.
(72)

选项 A、F-S
B、F-F
C、S-F
D、S-S

答案A

解析
转载请注明原文地址:https://jikaoti.com/ti/pRm7FFFM
0

相关试题推荐
最新回复(0)