The Estimate Activity Resource process i s closely coordinated with the(38) process.

admin2014-11-05  23

问题  The Estimate Activity Resource process i s closely coordinated with the(38) process.

选项 A、Estimate Costs
B、Sequence Activities
C、Plan Communications
D、Conduct Procurements

答案A

解析
转载请注明原文地址:https://jikaoti.com/ti/hPy7FFFM
0

最新回复(0)