Precedence Diagramming Method(PDM)is a method used in activity sequencing.There are four types of dependencies or precedence rel

admin2014-11-05  13

问题  Precedence Diagramming Method(PDM)is a method used in activity sequencing.There are four types of dependencies or precedence relationships in PDM.The initiation of the successor activity depends upon the completion of the predecessor activity is called(15).

选项 A、Finish-to.Start
B、Finish-to-Finish
C、Start-to-Start
D、Start-to-Finish

答案A

解析