(1)is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to repres

admin2009-05-15  30

问题 (1)is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activites and connects them with arrows that arrow the dependencies.This method includes following types of dependcies orprecedence relationships: (2)the initiation of the successor activity, depends upon the completion of the predecessor activity. (3)the initiation of the successor activity, depends upon the initiation of the predecessor activity.

选项 A、F-S
B、F-F
C、S-F
D、S-S

答案A

解析
转载请注明原文地址:https://jikaoti.com/ti/dqy7FFFM
0

相关试题推荐
最新回复(0)