(73) is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectan

admin2010-05-08  50

问题 (73) is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.

选项 A、PERT
B、AOA
C、WBS
D、PDM

答案D

解析
转载请注明原文地址:https://jikaoti.com/ti/NRS7FFFM
0

随机试题
最新回复(0)