The following diagram denotes dependency between two activities A andB.It says(75).

admin2016-09-08  32

问题 The following diagram denotes dependency between two activities A andB.It says(75).

选项 A、B can’t start before A is finished
B、B can’t finish before A is finished
C、B can’t start before A starts
D、B can’t finish before A starts

答案A

解析 本题目翻译:下图表示的活动A与B的依赖关系可以描述为(75)。
A.A结束前B不能开始;
B.A结束前B不能结束;
C.A开始前B不能开始;
D.A开始前B不能结束;
《按照系统集成项目管理师教程》,得到答案A。
转载请注明原文地址:https://jikaoti.com/ti/FUy7FFFM
0

最新回复(0)