In the process of communication requirement analysis, the project manager should consider the number of potential communication

admin2012-07-20  25

问题 In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communications. According to Metcalfe’s Law, a project with 10 stakeholders has ______ potential communication channels.

选项 A、 10
B、 45
C、 50
D、 100

答案B

解析