If the approved change requests have an effect on the proj ect scope,then the corresponding component documents and cost baselin

admin2016-11-11  54

问题 If the approved change requests have an effect on the proj ect scope,then the corresponding component documents and cost baselines,and___________of the project management plan,are revised and reissued to reflect the approved changes·

选项 A、developing baselines
B、testing baselines
C、schedule baselines
D、ending baselines

答案C

解析 如果已批准的变更请求对项目范围有影响,那么相应的文件和成本基线和(  )的项目管理计划也会修订来反映批准的变更。
A.发展基线    B.测试基线
C.进度基线    D.结束基线
转载请注明原文地址:https://jikaoti.com/ti/87y7FFFM
0

相关试题推荐
随机试题
最新回复(0)