Estimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities

admin2010-01-28  31

问题 Estimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.

选项 A、milestone
B、work
C、quality
D、baseline

答案B

解析
转载请注明原文地址:https://jikaoti.com/ti/wjS7FFFM
0

相关试题推荐
最新回复(0)