(2011年上半年)The earned value technique is a commonly used method of performancemeasurement.It integrates project scope,cost,and sc

admin2015-05-26  33

问题 (2011年上半年)The earned value technique is a commonly used method of performancemeasurement.It integrates project scope,cost,and schedule measures to help the projectmanagement team assess project performance.If a project’S Schedule Performance Index (SPI=EV/PV)  value less than 1.0,it means that (74).

选项 A、theprojectisaheadofitsplannedschedule
B、1essworkWascompletedthanwasplanned
C、thecostoverrullforworkcompleted
D、thecostunder-runofperformancetodate

答案B

解析 挣值分析技术是一种常用绩效测量方法。它集成了项目范围、成本、进度三方面的指标以帮助项目团队评估项目绩效。如果一个项目的进度绩效指数SPI小于1,则意味着进度落后。
转载请注明原文地址:https://jikaoti.com/ti/wbK7FFFM
0

相关试题推荐
最新回复(0)