首页
外语
计算机
考研
公务员
职业资格
财经
工程
司法
医学
专升本
自考
实用职业技能
登录
外语
Wolfe Constructions 121 Fifteenth Street Melbourne 200430 88880000 http: // www. Wolfeco
Wolfe Constructions 121 Fifteenth Street Melbourne 200430 88880000 http: // www. Wolfeco
admin
2011-06-01
29
问题
Wolfe Constructions
121 Fifteenth Street Melbourne 200430
88880000 http: // www. Wolfecon. com
Date: October 3, 2009
TO: Thomas S. Wolfe, President
From: Jack Evans, Project Manager
Subject: Progress on Hillcrest Apartments for September
Construction on the Hillcrest Apartment complex began on August 17 and fell behind schedule almost immediately because of the heavy rains that month.
Current Status
We have not been able to make up the time that we lost in August because of the continuing rain in September. Close supervision and some overtime have prevented us from falling farther behind. We are currently 18 days behind schedule, assuming crew size remains the same and overtime is limited to emergencies only. The foundation for the entire complex is complete. Framing on the 14# townhouse and the gym is complete, and the framers will begin work on the two-bedroom units on Monday, October 6. The electrical and plumbing subcontractors will also begin work on Monday.
Expected Progress
If the weather holds through the rest of this month, I expect to be finished with framing, roofing, and siding by mid-November. That will allow us to begin work on the interiors before the winter rains begin. One possible problem is the shortage of electricians. Our subcontractor has not been willing to consider providing an additional 5 workers to help us make up for some of the time we have lost. Delays on the electrical, will, of course, delay the finish work.
Nevertheless, when we move indoors, we should be able to reduce the total crew by more than 50 percent and begin using the framers and roofers on other projects.
Which of the following sentences can be inferred from the report?
选项
A、The reporter will dismiss the subcontractor sooner or later.
B、It will probably need more crew when dealing with the work indoors.
C、The work will fall farther behind if there is no extra electricians being added.
D、The framing, roofing, and siding is likely to have been finished by the middle of October if weather permitted.
答案
C
解析
转载请注明原文地址:https://jikaoti.com/ti/iMjsFFFM
本试题收录于:
托业阅读题库托业(TOEIC)分类
0
托业阅读
托业(TOEIC)
相关试题推荐
—WouldyoumindifIsitbesideyouforawhile?—_______.
Whowillmakeatelephonecall?
Mondayisthebeginningoftheworkweek;it’s【C1】_______daymostpeoplelike【C2】_______.It’snot【C3】_______thattheday
Alltheworkers______togetherandwrotealettertotheheadofthecompany.
Primecostsincludedirectmaterialscosts,directlaborcostsandindirectmanufacturingcosts.
Theemployerisvicariouslyliableforatortcommittedbytheemployeeactinginacourseofemployment.
Required,honour,dispatched,resulted,received,irrevocable,release,declared,prepared,handedGoodsshouldnotbe【21】di
Respondingtotheneedsofanagingpopulation,HealthNetwork,Inc.ofMelbourneandFuturaComputingofPerthAmboyhaveagree
PurchaseOrder#120-B21Date:4/6/07CreatingBetterLivingRoom1903,No521SouthWanpingR
Alargenumberofpeoplelivinghthecountrysidedependdirectlyorindirectly_____thetobaccobusiness.
随机试题
A、Helikestobelate.B、Helikestobeearly.C、Helikestobejustontime.D、Helikestobejustintime.B题目问的是说话者是哪一种人。由定位句
为了更好治疗,哪一项辅助检查是鉴别水肿型与出血坏死型的最好方法经治疗两周,体温仍持续在39℃以上,腹痛,腹胀,肠鸣音减弱,白细胞15×109/L,尿淀粉酶1200U,应考虑的合并症是
A4—8小时B8一12小时C1小时D2—4小时E12—24小时急性心肌梗死发作后LD开始升高的时间为
某16层建筑,每层面积为1000m2,在风力及地震作用下,倾覆力矩设计值为27000kN·m,已知荷载标准值:活载为1.5kN/m2,恒载为12kN/m2,平面重心距倾覆边缘的距离为x(m),以下x值中______项为满足抗倾覆要求的最小值。
下列属于完全互补性质的商品是()。
某城市社区居民对即将在本社区建设焚烧厂意见很大,认为垃圾焚烧会污染社会空气。因此,不少居民通过社区网上论坛表达不满情绪,有些居民还公开表示抗议,针对这种情况,该社区的社会工作者应当做的是()。[2013年真题]
学校教学工作中的“学科设置与安排”体现于()。
对比效应:指自己与别人相比较时,感觉到与比较目标的差距,从而产生消极的情感体验。与之相对的是投射效应,即在认知或对他人形成印象时,以为他人也具备与自己相似的特性,即推己及人的情形。根据上述定义,下列属于对比效应的是()。
甲发现去年丢失的电动自行车被路人乙推行,便上前询问,乙称从朋友丙处购买,并出示了丙出具的付款收条。如甲想追回该自行车,下列选项中,可以作为其理由来支持其请求的有
Noonedoubts______itistrue.
最新回复
(
0
)