( )is the process of identifying individual project risks as well as source of overall project risk, and documenting their ch

admin2020-08-10  34

问题 (    )is the process of identifying individual project risks as well as source of overall project risk, and documenting their characteristics.

选项 A、identify risks
B、monitor risks
C、impIement risks responses
D、plan risk management

答案A