The (73) provides the project manager with the authority to apply organizational resources to project activities.

admin2010-01-28  49

问题 The (73) provides the project manager with the authority to apply organizational resources to project activities.

选项 A、project management plan
B、project charter
C、project human resource plan
D、project stakeholders

答案B