Each box is an activity; the number it contains is the duration of the activity in days. The duration of the critical path is(75

admin2008-08-01  38

问题 Each box is an activity; the number it contains is the duration of the activity in days. The duration of the critical path is(75)

选项 A、16days
B、14days
C、19days
D、20days

答案C

解析 关键路径为最长时间的线路,3+6+7+1+2=19。
转载请注明原文地址:https://jikaoti.com/ti/N0x7FFFM
0

最新回复(0)