杭州月亮有限公司Hangzhou Moon Co.Ltd.是一家流通性外贸企业,2005年12月15日收到德国KKK Co.Ltd.的订单如下: ORDER NO.:040426 DATE:14Dec,2005 SUPPLIER:H

admin2010-05-08  25

问题 杭州月亮有限公司Hangzhou Moon Co.Ltd.是一家流通性外贸企业,2005年12月15日收到德国KKK Co.Ltd.的订单如下:
   ORDER NO.:040426
   DATE:14Dec,2005
   SUPPLIER:Hangzhou Moon Co.Ltd。
   ADDRESS:NO.118 Xueyuan Street,
            Hangzhou,China
   DESCRIPTION OF GOODS:
   LADIES JACKET,woven,fur at collar,with bronze-coloured buttons,2 pockets ai front
   and 2 pockets without flaps at chest,inside pocket&inside mobile phone pockets.like
   original sample but without flaps ai chest.
   CoUNTRY OF ORIGIN:China
   CODE NO.:6202920000
   DOCUMENTS:Certificate of Origin
   QUALITY:
   Shell:100%cotton twill 20 16/128 60,reactive dyed,stone washed
   Lining:100%polyester 230T
   Padding:100 polyester,body 140g,sleeve 120g
   UNIT PRICE:USD7.10 per piece FOB SHANGHAI
   QUANTITY:14400pcs
   AMOUNT:USDl02240.00
   More or lessl%of the quantity and the amount are aiiowed.
   TERMS OF PAYMENT:
   L/C 60days after B/L date
   DATE AND WETHOD OF SHIPMENT:20 Jun.,2006-30Jun.,2006 by sea;otherwise
   1 Jul.,2006 on seller’s account by air.
   PORTOF LOADING:SHANGHAI
   PoRT OF DESYINATION:HAMBURG
   PARTAL SHIPMENT:PROHIBITED
   FORWARDING AGENT:Kuehne und Nagel

PURCHASE CONDITIONS :
   Attn.-AZO and Nickel.
   The import and of products with AZO- colours nickel accessories into Germany is strictly forbidden.
   The supplier warrants that manufacture of the delivered goods has not involved work by children in an exploiting, health-endangering or slave-like manner, forced labour or exploitative prison work.
   The material composition of each article has to be advised; for garments on the sew-in label in following languages. German, English, Spanish and French, fornontextiles in the packing according to the special instructions which will be specified for each individual order.
   f the labeling or pricing of the goods is not correct, we will debit the supplier 3%of purchase price.
   Place of performance and court of jurisdiction. Dortmund/Germany.
   SHIPPING MARKS.
   O40426
   KKK
   BREMEN
   C.NO.:1-UP
   SIDEMARKS:
   LIEF-NR:70019
   AUFTR.NR:040426
   EKB:DOB1
   WGR.:938
   ST/KRTN1/:8
   SIGNATURE:                          SIGNATURE:
         (SELLER)                            (BUYER)  
A工厂是从2006年5月5日(星期五)开始生产案例1订单的产品,每周工作5天,每天2个班次,每个班次工作8小时,下面是该厂的生产日报表(其中废品以扣除)。

以后几天都是按照这个速度生产,直到5月22日(星期一)为止。

从5月23日开始到5月26日,由于电力紧张,致使每天只能工作12小时。

跟单员在5月26日发现用电紧张情况后,应该如何处理?

选项

答案(1) 通过对A工厂生产日报表分析,服装生产的裁剪、缝制、后道和包装四个生产环节中,缝制是决定生产速度的关键环节,因此只要没有发生人员变动的情况下,缝制能完成数量,则可以基本保证能完成全部产量,因此下面把缝制环节看作服装的产量。 (2) 由于电力紧张,5月23日开始到5月26日,每天工作时间从原来的16个小时降到12小时,导致日产量从450件降到350件。如果按照这样的生产进度(每天350件),则剩余要生产的数量14400-6620=7780件,需要的工作日为:7780÷350=22.22≈23个工作日,若仍然按照一周工作5台你算,则要到6月28日完成,若再遇上其他问题,就很有可能不能在6月30日之前如期出运,若在7月1日至7月15日之间才出运,根据订单的规定,就必须要采用空运,空运费将由我方承担。 (3) 因此作为跟单员必须要会同A工的有关管理人员,调整生产计划。可以采用以下措施:调整一周的工作天数,从5月27日(星期六)开始,每周工作7天,若没有出现其他异常情况,剩余产品可以在6月16日完成生产。这样就能在规定的交货期内完成生产。

解析
转载请注明原文地址:https://jikaoti.com/ti/LdBVFFFM
0

最新回复(0)