From: Lyle Martin To: Jerry Mason Re: Tiles Date: July 20 Dear Mr. Mason The maintenance manager has asked me to let you know

admin2015-09-22  30

问题 From: Lyle Martin
To: Jerry Mason
Re: Tiles
Date: July 20
Dear Mr. Mason
The maintenance manager has asked me to let you know that due to the flood damage we will have to have most of the tiles in your assembly line replaced. The installation is going to begin tomorrow but since the area is so large and so much equipment needs to be moved around, they will not finish laying down the tiles until Monday afternoon, July 23.
Unfortunately we’re unable to provide an alternative place for the personnel from the assembly line to work during that time, so you’re being asked to report back to work by 10: 00 on Tuesday morning. If the installation takes more or less time than we anticipated, you will be informed by phone.
Lyle Martin
When will the construction begin?

选项 A、On July 20.
B、On July 21.
C、On July 22.
D、On July 23.

答案B

解析 文中提到明日开始但电子邮件的发送日期是7月20日所以工程开始日期是7月21日的(B)。
转载请注明原文地址:https://jikaoti.com/ti/8vRsFFFM
0

最新回复(0)