Several risk response strategies are available.____________the risk simply gives another party responsibility for its management

admin2013-08-12  43

问题 Several risk response strategies are available.____________the risk simply gives another party responsibility for its management,it does not eliminate risk.

选项 A、Avoiding
B、Mitigating
C、Accepting
D、Transferring

答案D

解析 当只有部分风险应对措施可以选择时,转移风险只是提供了另一种管理方式,它并不能消除风险。因此选择Transferring。