(75) are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result

admin2010-01-28  45

问题 (75) are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.

选项 A、Project manager
B、Project stakeholders
C、Sponsor
D、Project team member

答案B

解析