When required,the Perform Integrated Change Control process includes a (74)________,which is a formally chartered group responsi

admin2021-03-25  31

问题   When required,the Perform Integrated Change Control process includes a (74)________,which is a formally chartered group responsible for reviewing,evaluating,approving,deferring,or rejecting changes to the project and for recording and communicating such decisions.

选项 A、BBC
B、CCB
C、BCB
D、CBC

答案B

解析 必要时,应该由变更控制委员会(CCB)来开展实施整体变更控制过程。CCB是一个正式组成的团体,负责审查、评价、批准、推迟或否决项目变更,以及记录和传达变更处理决定。
转载请注明原文地址:https://jikaoti.com/ti/2AS7FFFM
0

相关试题推荐
最新回复(0)