The Perform Integrated Change Control process is conducted from proj ect inception through completion and is the ultimate respon

admin2015-11-01  14

问题 The Perform Integrated Change Control process is conducted from proj ect inception through completion and is the ultimate responsibility of the _______.

选项 A、Chang control board
B、Project management office
C、Project manager
D、Configuration management officer

答案C

解析 项目经理的职责。执行综合变更控制过程是从项目开始到完成,这也是项目经理的职责。
转载请注明原文地址:https://jikaoti.com/ti/x8K7FFFM
0

最新回复(0)