首页
外语
计算机
考研
公务员
职业资格
财经
工程
司法
医学
专升本
自考
实用职业技能
登录
计算机
Project schedule management is made up of six management processes including:activity definition,activity sequencing,(71),and sc
Project schedule management is made up of six management processes including:activity definition,activity sequencing,(71),and sc
admin
2015-04-27
60
问题
Project schedule management is made up of six management processes including:activity definition,activity sequencing,(71),and schedule control by order.
Many useful tools and techniques are used in developing schedule.(72)is a schedule network analysis technique that modifies the project schedule to account for limited resource.
Changes may be requested by any stakeholder involved with the proj ect,but changes can be authorized only by(73).
Configuration management system can be used in defining approval level s for authorizing changes and providing a method to validate approved changes.(74)is not a project configuration management tool.
Creating WBS means subdividing the major project deliverable into smaller components until the deliverable are defined to the(75)level.
(72)
选项
A、PERT
B、Resource leveling
C、schedule compression
D、critical chain method
答案
D
解析
转载请注明原文地址:https://jikaoti.com/ti/wNN7FFFM
本试题收录于:
信息系统管理工程师上午基础知识考试题库软考中级分类
0
信息系统管理工程师上午基础知识考试
软考中级
相关试题推荐
某公司需要根据下一年度宏观经济的增长趋势预测决定投资策略。宏观经济增长趋势有不景气、不变和景气3种,投资策略有积极、稳健和保守3种,各种状态的收益如表16-12所示。基于maxmin悲观准则的最佳决策是(67)。
通常软件项目管理活动包括项目的计划、调度、通信、费用估算、资源分配以及质量控制等,软件生产是智力密集型的活动,其产品无物理外形,生产状态也“不可见”,因而难以检查和驾驭。软件项目管理工具就是要使这种生产过程成为可见、可控的过程。因此,软件项目管理工具应具备
传输一幅分辨率为640×480,6.5万色的照片(图像),假设采用数据传输速度为56kb/s,大约需要______秒钟。A.34.82B.42.86C.85.71D.87.77
某软盘有40个磁道,磁头从一个磁道移至另一个磁道需要5ms。文件在磁盘上非连续存放,逻辑上相邻数据块的平均距离为10个磁道,每块的旋转延迟时间及传输时间分别为100ms和25ms,则读取一个100块的文件需要______时间。A.5000msB.150
关于网络安全,以下说法中正确的是______。
SSL-VPN可利用Web浏览器标准配置的SSL加密功能来保证数据通信的安全性。以下关于SSL-VPN说法中,错误的是______。
Estimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule acti
The(72)technique involves using project characteristics in a mathematical model to predict total project costs. Models can be si
()isadecentralized,distributedandpublicdigitalledgerthatisusedtorecordtransactionsacrossmanycomputersSO
Virtualreality(orVR(1)iskindofabuzzwordthesedaysincomputergraphics.VRisartificialrealitycreatedbyacomputertha
随机试题
建筑工程在施工过程中,发生()变更的情况,应当重新申请领取施工许可证。
男,35岁。反复咳嗽伴呼吸困难20年,再发1天,吸入“万托林”或口服“氨茶碱片”后可缓解。查体:双肺闻及干啰音。外周血WBC7.8×109/L,E0.15。与该病发生关系最密切的免疫球蛋白是
某大型商品房建设项目开始组织工程施工招标,招标人对招标过程的时间及内容安排如下:(1)2010年12月27日(周一)发布招标公告,并规定2010年12月28日至2011年1月3日9:00~17:00发售招标文件。(2)投标人购买招标文件
路堤的填筑应优先选用()。
单元工程或工序质量经鉴定达不到设计要求,经加固补强后,改变外形尺寸或造成永久性缺陷的,经建设(监理)单位认为基本满足设计要求,其质量可按()处理。
钢筋分项工程质量控制的检查项目有()。
下列交易或事项产生的现金流量中,属于筹资活动产生的现金流量的有()。
清朝编纂的我国最大的一部丛书是()。
2018年8月,国家提出衡量贫困人口是否脱贫的标准是“两不愁、三保障”,其中“两不愁”是指不愁吃、不愁穿。以下不属于“三保障”的是:
2011年世界大学生运动会在中国深圳举行,运动员通过各国的选拔来参加比赛。某项目限制每个国家最多两个报名名额。某国在该项目上有四名出色的运动员U、V、W、X愿意报名参赛。通过一次公平、公开、公正的国内比赛,选拔出U、V参加世界大学生运动会。以下所列各项陈述
最新回复
(
0
)