Youareaprojectmanagerforasmallproject.Yourprojectwasbudgetedfor¥500,000overasix-weekperiod.Asoftoday,you’vespent¥260,000ofyourbu

admin2012-03-22  30

问题 Youareaprojectmanagerforasmallproject.Yourprojectwasbudgetedfor¥500,000overasix-weekperiod.Asoftoday,you’vespent¥260,000ofyourbudgettocompleteworkthatyouoriginallyexpectedtocost¥280,000.Accordingtoyourschedule,youshouldhavespent¥300,000bythispoint.Basedonthesecircumstances,yourprojectcouldbebestdescribedas______.

选项 A、aheadofschedule
B、behindschedule
C、onschedule
D、havingnotenoughinformationprovided

答案B