On America’s Gulf coast, massive industrial facilities stand idle. Miles of twisting stainless-steel pipes and huge storage tank

admin2018-03-01  12

问题     On America’s Gulf coast, massive industrial facilities stand idle. Miles of twisting stainless-steel pipes and huge storage tanks gleam uselessly in the sun. They are a reminder of the hundreds of billions of dollars that America has invested in terminals for handling imports of liquefied natural gas (LNG). Thanks to the boom in domestic shale gas, those imports are no longer needed. America produces nearly as much gas as it consumes, and will soon produce far more.
    So the obvious thing to do with those idle terminals is to re-engineer them to handle exports. Instead of receiving shiploads of liquefied gas and re-gasifying it, they should be taking American gas, liquefying it and loading it onto tankers. Converting these plants will not be cheap—each one will cost at least $5 billion. But the potential rewards are much larger.
    In America gas sells for around $3.40 per million British thermal units (mBTU). In Europe it costs around $12. In gas-poor Asia, spot cargoes change hands for as much as $20 per mBTU. Since it costs roughly $5 per mBTU to liquefy the stuff, ship it and turn it back into gas, America could be making a fortune from gas exports. To the extent that such exports displaced dirty coal, they would also help curb global warming.
    Most of America’s two dozen LNG import terminals have applied for export licences. Yet only one, Sabine Pass in Louisiana, has actually started retooling its kit. Gas from there will start flowing onto global markets by the end of 2015. Why has every other terminal been so slow to seize this opportunity?
    Converting a plant is not easy: firms must build now upon row of expensive fridges, known as "liquefaction trains", to get gas moving in the opposite direction. But the real hold-up is political. No LNG facility besides Sabine has yet received permission to export. American law requires the Department of Energy to determine whether gas exports are in the public interest, and President Barack Obama’s administration is in no hurry to make up its mind.
We can judge from the last paragraph that ______.

选项 A、no LNG facility except Sabine has gained permission to export
B、gas exports in America represent the interest of the public
C、Barack Obama’s government has made up its mind
D、a plant is difficult to be converted

答案D

解析 根据选项A中的“No LNG facility”定位到该段第三行:No LNG facility besides Sabine has yet received permission to export. 表面看该选项和原文几乎一致,其中“gained permission”=“received permission”。但选项中出现了except,原文说的是besides。注意两词有本质区别:except是“除了……之外”;besides强调“包括在内”。故选项A错误。根据选项B中的“interest of the public”定位到第四行:American law requires the Department of Energy to determine whether gas exports are in the public interest. 原文关于天然气出口是否代表公众利益并没有给出答案,而选项B项说:天然气出口代表了公众利益。故错误。根据选项C中的“Barack Obama”定位到最后一句:President Barack Obama’s administration is in no hurry to make up its mind.关键词是“in no hurry(不急着做决定)”,选项C说“has made up its mind(已经作好决定)”,故错误。D项对应该段第一句:Converting a plant is not easy. 选项D与该句属于同义转换关系,故为答案。
转载请注明原文地址:https://jikaoti.com/ti/qtX7FFFM
0

随机试题
最新回复(0)