In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including (26).

admin2009-09-20  32

问题 In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including (26).

选项 A、budget
B、plan
C、risk
D、contract

答案C

解析 在估算成本时,估算者会考虑成本估算偏差的潜在原因,包括风险。
转载请注明原文地址:https://jikaoti.com/ti/oyy7FFFM
0

相关试题推荐
最新回复(0)