Developing the project schedule is often an iterative process.It determines the planned start and finish dates for project activ

admin2014-11-05  23

问题  Developing the project schedule is often an iterative process.It determines the planned start and finish dates for project activities and milestones.Schedule development can reqmre the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(40) progress.

选项 A、analyze
B、track
C、1evel
D、extend

答案B

解析
转载请注明原文地址:https://jikaoti.com/ti/lPy7FFFM
0

随机试题
最新回复(0)