The Estimate Activity Resource process i s closely coordinated with the(38) process.

admin2014-11-05  30

问题  The Estimate Activity Resource process i s closely coordinated with the(38) process.

选项 A、Estimate Costs
B、Sequence Activities
C、Plan Communications
D、Conduct Procurements

答案A

解析