(51) from one phase are usually reviewed for completeness and accuracy and approvedbefore work starts on the next phase.

admin2019-06-06  51

问题 (51) from one phase are usually reviewed for completeness and accuracy and approvedbefore work starts on the next phase.

选项 A、Process
B、Milestone
C、Work
D、Deliverables

答案D

解析