Your project is behind schedule due to conflict between team members.Having resolved theconflict.to get the project back on sche

admin2019-06-06  46

问题 Your project is behind schedule due to conflict between team members.Having resolved theconflict.to get the project back on schedule,you should consider(3).

选项 A、crashing the schedule
B、performing resource leveling
C、conducting reverse resource allocation scheduling
D、utilizing the critical chair resources

答案B

解析