Estimate activity duration is the process of estimating the number of work periods to complete activities with estimated resourc

admin2019-08-25  46

问题 Estimate activity duration is the process of estimating the number of work periods to complete activities with estimated resources.The tools and technique is not including(        ).

选项 A、expert judgment
B、analogous estimating
C、requirements traceability matrix
D、three-point estimating

答案C

解析 翻译:估算活动的持续时间是估算在有限的资源内完成单项活动所需工作时间段数的过程,所需的工具技术不包括需求跟踪矩阵。
    A.专家判断    B.类比估算    C.需求跟踪矩阵    D.三点估算