The Estimate Activity Resource process is closely coordinated with the(73) process.

admin2010-01-17  44

问题 The Estimate Activity Resource process is closely coordinated with the(73) process.

选项 A、Estimate Costs
B、Sequence Activities
C、Plan Communications
D、Conduct Procurements

答案A

解析 估算活动资源与成本估算是密切联系的。