A project manager believes that modifying the scope of the project may provide added value service for the customer.The project

admin2011-01-29  36

问题 A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.

选项 A、assign change tasks to project members
B、call a meeting of the configuration control board
C、change the scope baseline
D、postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

答案D

解析 项目经理认为调整项目范围可以给客户提供增值的服务,项曰经理应该怎么做。
   选项A是安排任务变更到项目成员,选项B是召集变更控制委员会会议,选项C是变更项目基线,选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。
   由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金,因此应选择D。
转载请注明原文地址:https://jikaoti.com/ti/QRS7FFFM
0

随机试题
最新回复(0)