_______________is a proj ect management technique for measuring proj ect performance and progress.It has the ability to combine

admin2018-05-26  35

问题 _______________is a proj ect management technique for measuring proj ect performance and progress.It has the ability to combine measurements of the project management triangle:scope,time and costs.

选项 A、Critical path method(CPM)
B、Earned value management(EVM)
C、Net present value method(NPVM)
D、Expert judgment method(EJM)

答案B

解析 挣值管理(EVM)是把范围、进度和资源绩效综合起来考虑,以评估项目绩效和进展的方法。它是一种常用的项目绩效测量方法。它把范围基准、成本基准和进度基准整合起来,形成绩效基准,以便项目管理团队评估和测量项目绩效和进展。