During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate.This

admin2016-11-11  31

问题 During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate.This duration is what you commit to complete the project.What is wrong with the scenario?___________.

选项 A、The team did not create the estimate and estimating takes too long using that method
B、The team did not create the estimate and a network diagram was not used
C、The estimate is too long and should be created by management
D、The project estimate should be the same as the customer′S required completion date

答案B

解析 在规划期间你坐下来,估计每个任务所需的时间并合计形成项目估计时间。这段时间是你承诺要完成这项工程的时间。什么是错误的场景?
A.团队并没有创造估计和估算的时间太长,使用该方法
B.团队没有创建估计和未使用网络图
C.估计时间太长,应由管理进行
D.项目估计应与客户的要求的完成日期相同
转载请注明原文地址:https://jikaoti.com/ti/9gS7FFFM
0

相关试题推荐
最新回复(0)