In all projects,needs must be tempered by schedule,cost and resource constraints.Project success depends primarily on ( ).

admin2016-05-11  52

问题 In all projects,needs must be tempered by schedule,cost and resource constraints.Project success depends primarily on  (   ).

选项 A、the quality of the schedule and cost control analysis
B、customer satisfaction
C、customer compromise in defining its needs
D、exceeding customer requirements through gold—plating

答案B

解析 所有项目中,客户的要求必须根据进度表、成本和有限的资源进行修改。项目的成功主要取决于:
    A 进度表和成本控制分析的优劣
    B 客户满意程度
    C 客户在确定要求时的折衷态度
    D 通过漂亮的外包装超额满足客户的要求
    所以答案选B。