(2011年下半年)The project schedule is more than a document that lays out the activities overtime to represent the time dimension of

admin2015-05-26  38

问题 (2011年下半年)The project schedule is more than a document that lays out the activities overtime to represent the time dimension of the project,it is a management tool to be used for decision making.As such,the schedule is used by the project management team to(73).

选项 A、Measure,delay,record,distribute,analyze,anddirect
B、planschedule,monitor,control,report,andforecast
C、Promote,highlight,monitor,control,forecast,andreport
D、Emphasize,visualize,analyze,conceptualize,reportandrecord

答案B

解析 项目进度计划不仅是一个划定了活动的时间从而在时间维度上描述项目的文档;它更是一个用于决策制定的管理工具。因此,进度计划被项目管理团队用来进行项目计划、时间调配、监测、控制、报告和预测。
转载请注明原文地址:https://jikaoti.com/ti/7HK7FFFM
0

相关试题推荐
最新回复(0)