The project manager must maintain an effective communication link with the customer’s satisfaction with the progress of the proj

admin2012-03-26  14

问题 The project manager must maintain an effective communication link with the customer’s satisfaction with the progress of the project. The project manager maintains this link through______.

选项 A、periodic project reports, periodic visits to the customer, and telephonic exchanges
B、subordinates, project team members, and the project sponsor
C、one-time reports, weekly reports, and monthly reports
D、the telephone, facsimile, and data transmission

答案A

解析 项目经理必须保持一个有效的沟通渠道,以使客户对项目的进展表示满意。项目经理可以通过定期的项目报告(periodicprojectreports)、定期走访客户(periodicvisitstothecustomer)和电话交流(telephonicexchanges)等保持这个渠道。
转载请注明原文地址:https://jikaoti.com/ti/c7S7FFFM
0

最新回复(0)