The responsible pefiod of the carrier for the loss of or damage to the cargo as well as delay indelivery under CMR convention is

admin2009-01-22  48

问题 The responsible pefiod of the carrier for the loss of or damage to the cargo as well as delay indelivery under CMR convention is between(  ).

选项 A、the port to port
B、the door to door
C、the rail to rail
D、the time the cartier taking over the goods and the time of delivery

答案D

解析 根据《国际公路货物运输合同公约》(CMR convention)的规定,承运人的责任期间为从接收货物时起到交付货物时止。
转载请注明原文地址:https://jikaoti.com/ti/XMKVFFFM